Austrian Lotteries – Austria
Type of project:
Sport- / Recreational- / Eventcenter
Segment:
Renovation
Product group:
ARDEX S 28, ARDEX A 35, ARDEX 8+9, ARDEX G8S If you enter the new headquarters of Austrian Lotteries you set a foot on quality handiwork from ARDEX. The whole entrance area and the event location ‘Loft’ were completely redesigned. Several products of the ARDEX assortment were used on the overall 400 m2 surface. To reach a perfect result, the headquarter was equipped with ARDEX S 28 (specializing in laying big slabs), ARDEX A 35, ARDEX 8+9 and the grouting compound ARDEX G8S. Graphite-coloured tiles of the Concrete-series produced by GigaChair were laid on these 4.8 mm thick 1.20 x 1.20 m slabs. Responsible for the professional execution was the company Sturgyk who is an established partner of ARDEX. The Result? See for yourself!
Raffles City Swissotel Helipad Waterproofing – Singapore
Project Name:
Raffles City Swissotel Helipad Waterproofing, Singapore
Installer/Applicator:
LH Waterproofing Specialists Pte Ltd, Singapore
General Contractor:
Shineway Engineering Pte Ltd, Singapor
Consultant:
Arup Singapore Pte Ltd, Singapore
Featured Products:
ARDEX R 2 SE
ARDEX WPM 426
ARDEX WPM 429
Challenge:
- Reinforced Concrete Rooftop Helipad Waterproofing (570m2)
- Short completion day (5 days including surface preparation)
- Exposed to weather environment
- Existing commercial environment with restaurant right below, so required to minimize inconvenience caused for customers and tenants while conducting works
- Heavy duty wear and abrasion resistance for helicopter landing
Situation:
Raffles City is going through re-roofing works for its entire Reinforced Concrete planters and flat roofs using ARDEX WPM 116 and WPM 160, two layers torched applied waterproofing membrane. The RC rooftop helipad is a critical area as any hacking on the RC slab to lay new waterproofing membranes might cause leakage to the restaurant below. The landing zone lightning built into the RC slab make the detailing works for installing new membranes difficult and tedious.
Solution:
After having reviewed the problem and client’s concerns, ARDEX Singapore recommended ARDEX WPM 426 and WPM 429 (UV stable Polyurethane Traffic Deck Waterproofing Coating). The system perfectly suits to resolve the challenges faced. ARDEX WPM 426 is a heavy duty and abrasion resistance waterproofing coating with ARDEX WPM 429 UV stable aliphatic topcoat to coat over the RC helipad to give a new decorative look including waterproofing properties.
Unique Elements:
ARDEX Singapore provides the complete system solution through specifications to Arup consultants for this project. The installation was done by an approved and trained ARDEX applicator. However, there were frequent site visits by the Sales personal in charge to provide excellent service. Together with the outstanding performance of the products, with no defect or limitation, the clients are very satisfied with ARDEX. Consequently, consultants and contractor continued to specify the ARDEX system for upcoming projects’ e.g.: Global Logistic Trade Center façade refurbishment project, condominium refurbishment project and many more.
Mandarin Oriental Hotel – Thailand
Featured Installer:
Thai Her Chern Marble & Granite Co., Ltd.
General Contractor:
Task Interior Co., Ltd.
Featured Products:
- ARDEX CT 5 Commercial Tile Adhesive
- ARDEX DS 40 Impact Sound Reduction and Decoupling System
Challenges:
- Installing large, natural stone tiles on walls and floors in bedroom and restroom areas
- Installer and contractor education was necessary, as they were unfamiliar with ARDEX products
Situation:
Mandarin Oriental Hotel is considered the most prestigious and luxurious hotel in Bangkok city. Since its establishment in 1879, renovations occur with some frequency on a regular basis. This particular renovation included 30 rooms, had a duration of four months, and was completed in February, 2016. As a high-end 5-star hotel, the property was expected to be renovated according to the highest specification standard with premium products. Natural stone was chosen as the primary material to maximize the charm of hotel’s modern interior design. Task Interior Company, the contractor, also wished to install a high-performance soundproof system that can effectively reduce the sound and create the best atmosphere for hotel guests.
Solution:
ARDEX CT 5, a tile adhesive, was specified as a reliable solution for this project. In order to educate the installer, as well as exhibit the product’s superior performance, a product demonstration was held. Satisfied that the product exceeded the others available in the Thai domestic market both in technical properties and ease of installation, the contractor used the adhesive throughout the project with great success. ARDEX also proposed ARDEX DS 40, an Impact Sound Reduction and Decoupling System, to the General Contractor. In addition to their sound reduction properties, the pre-cut mats simplify installation and have excellent crack-bridging ability. ARDEX Singapore technical staff visited the job site to demonstrate correct installation procedures for ARDEX DS 40, and resulted in the mats being specified for the entire project. They were installed, where needed, for the entire renovation project with no difficulties.
Banyan Tree Club & Spa – Korea
Installer:
General Contractors:
- Ssangyong Engineering & Construction Co., Ltd. – Seoul, South Korea
Architects:
- Gansam Partners Architecture Design and Planning
Product Featured:
- PANDOMO® Wall (PANDOMO W1) Decorative Finishing Render
- PANDOMO® TerrazzoMicro
- ARDEX F5 Fiber Reinforced Finishing Compound
Challenges:
- Expedited installation time frame
- Multiple contractors on site
- Cold exterior temperatures
- Cracking and uneven surfaces
Problem:
Originally opened in 1969, the Namsan Tower required a complete remodel and transformation to become a world-renowned resort chain – The Banyan Tree Club & Spa. This was the first South Korean remodeling project of its kind, transforming an existing 2-Star tower into a high-end 5-Star resort. When remodeling requires a high-end result, it calls for best-in-class products. ARDEX Pandomo® systems were specifically selected because of the high-end quality, design capabilities and modern elements of the products. However, because of multiple contractors on site, it made for a difficult installation of PANDOMO® Wall. The developer of the project also requested Pandomo® materials be used on the building exterior. Pandomo® Wall is specifically designed for interior applications; so the ARDEX Technical Team worked with the contractor to find a solution.
Solution:
In the hotel rooms, swimming pool area, and restaurant, C & P Stone worked through the night after other companies left for the evening. Working at night allowed the installers to properly clean the walls before installing ARDEX PANDOMO® Wall and reduce the amount of airborne particles found on a busy construction site with potential to contaminate the installation. Once the contractors finished with a section of the installation, the area was completely sealed with vinyl sheeting to prevent any contamination. A few sections were reinstalled because of damage caused by heavy equipment from other construction. ARDEX PANDOMO® Wall was selected because of its fast track properties, versatility, simple elegance and ability to create a seamless finish. In the elevator hall, installers were challenged with an uneven, cracked substrate. To rectify these problems and prepare the floor to receive ARDEX PANDOMO® TerrazzoMicro, cracks were sealed and primed with an epoxy primer to include a sand broadcast. Once cured, the previously unsuitable substrate received its new terrazzo style flooring. ARDEX PANDOMO® TerrazzoMicro was specified in this area because of its natural beauty and fast-curing properties. ARDEX PANDOMO® TerrazzoMicro was open to traffic in roughly eight hours, allowing appropriate cure time before additional workers arrived the next day. For exterior signage, the developer wanted to use ARDEX PANDOMO® Wall, but there were some concerns from the ARDEX Technical Team about the performance of the product in an environment with four extremely different seasons. The ARDEX Technical Team recommended ARDEX F5 Fiber reinforced finishing compound instead. ARDEX F5 is especially suited for indoor and outdoor use on walls and ceilings. Largely, because ARDEX F5 can be used as a repair mortar and fill any holes, cavities or unevenness as the rendering was being applied. Once completed, this 2-Star hotel was transformed into a 5-Star resort. The ARDEX products that were installed added to the unique, modern design of the Banyan Tree Hotel.
Varyap Meridian – Istanbul Turkey
Applicator:
Artun İnşaat – İstanbul İnşaat – Decons İnşaat
General Contractor:
Varlıbaşlar Holding
Architect:
RMJM Mimarlık & TRAFO Mimarlık & DOMEMimarlık
Products Featured:
- ARDEX X7G (15.600 m²)
- DUNLOP Tile Adhesive (98.000 m²)
- ARDEX P51 Primer (15.600 m²)
Story:
Varyap Meridian is a project for which a competition has been organzied with the enrollment of renowned architecture firms. The winning project was submitted by RMJM / NY’s, a British origin company that proves itself on not only with its architectural designs but also with its skills on urban planning and creating new urban areas in different parts of the world. The unique design that rises with a multinational team consisting of 150 members and emphasising the historical peninsula of Istanbul turned out to one of the most exclusive realty projects & brands of Istanbul with its high technology infra&superstructure. Having 11 important international awards with its unlikely & sustainable design, Varyap Meridian finally won “The Best Architecture Project of the World” prize in International Property Awards 2010.
Challenges:
- Very thin (4-5mm) Villeroy & Boch Tiles were chosen to use in wet areas due to a wallpaper covering starting at 1.2m level.
- Due to the wallpaper, the final render of the wall was a plaster surface.
- A strong & flex tile adhesive was required to apply those thin tiles without thickening the surface (6mm trowel size)
- The water absorbent plaster surface results that the adhesive dries rapidly which makes it a challenge for the application.
Solution:
- To decrease the water absorption of the wall surfaces ARDEX P51 Primer was applied (1:3 dilution ratio)
- With its fast & easy application as well as its fast drying time, ARDEX P51 Primer made it easy to prepare the surface for the tile adhesive application.
- ARDEX X7G was the chosen product by overcoming the competitors with its extraordinary adhesion power, flexibility and a coverage of 13m²/bag, which was surprising the project authorities.
Burj Khalifa – Middle East
Teams:
- ARDEX Middle East
- ARDEX UK Installer:
- Floortec Arabia Technical Services LLC – Dubai, United Arab Emirates
Contractor:
- Samsung C&T Engineering & Construction Group – Seocho-Gu Seoul, Korea
Architects:
- Skidmore, Owings & Merrill (SOM) – Chicago, IL (USA)
- Holford Associates – Dubai, United Arab Emirates
Product Featured:
- ARDEX ARDITEX NA Latex Sub-Floor Levelling & Smoothing Compound
Challenges:
- Fast-track time line
- Tallest building in the world – 828m (2,716.5 ft.)
- Water not readily available for mixing on upper floors during construction
- Concerns of water spillage during site mixing
- Earlier attempts with competitors products caused wood floors to warp
- Concerns of scarifying the concrete slabs in preparation for Self-Leveling Underlayments up to 186 floors
Problem:
Housing a hotel, residential units, corporate suites, restaurants and many leisure areas; the Burj Khalifa is not only the tallest building in the world, but also a state-of-the-art destination. So when problems arose during the construction, ARDEX Middle East was called upon to provide recommendations and implement a solution. Earlier attempts with competitors’ products left this landmark falling short of expectations with wood flooring failures caused by moisture in the concrete underlayment and water spillage during the mixing process.
Solution:
Offering a full guarantee, ARDEX Middle East worked with the ARDEX UK Technical Team to recommend ARDITEX NA Self-Smoothing Compound. This ammonia free formula product is used to level uneven internal sub-floors, creating a smooth surface, by using a pre-formulated additive and not requiring water. ARDITEX NA also saved time because it can be placed over strongly bonded existing adhesive residues and allows floor coverings to be placed after four hours. Time was also saved since the need for water to be transported from the ground up to each level was eliminated.
Oracle Broadbech Apartments – Australia
Installer/Applicator:
- BAT Tiling – Caboolture, Queensland, Australia
General Contractors:
- Niecon Developments Pty Ltd. – Gold Coast, Queensland, Australia
Architect:
- Niecon Developments Pty Ltd. – Gold Coast, Queensland, Australia
Product Featured:
- ARDEX WPM 002 Superflex Bathroom and Balcony Two Part Under Tile Waterproofing Membrane
- ARDEX WPM 155 Undertile PU Acrylic Hybrid Membrane
- ARDEX Multiprime Water-Based Primer
- ARDEX Abacrete Bonding Agent (for Use with Sand / Cement Screeds and Renders)
- ARDEX Abaflex Premium Polymer Modified Flexible Tile Adhesive
- ARDEX X 10 Flexible Non Slump Wall and Floor Tile Adhesive
- ARDEX White Grout Fine Textured Wall Tile Grout
- ARDEX Wide Joint Grout White
- ARDEX FG 8 Flexible colored grout (for tile joints 1 to 8 mm wide)
- ARDEX DS 40 Impact Sound Reduction and Decoupling Systems
- ARDEX AF 266 Outdoor Grass Carpet Adhesive
Challenges:
- One 40 level and one 50 level tower
- Mixed use development
- Multiple tile applications
Problem/Situation:
As part of a redevelopment plan to turn Broadhead Beach into a high-end ‘live-work-play’ destination, an $850 million investment was provided to build two modern towers, the Oracle Broadbeach Apartments. Niecon Developments specified ARDEX products as the solution to this challenge. In doing so, they received complete peace of mind knowing ARDEX tile adhesives are high quality products compatible with marble, vitrified and ceramic tile. The Oracle Beach Apartments consisted of a 40 and a 50 level tower. The two towers were new construction and tile was to be used throughout the majority of the interior spaces. The building consisted of residential, retail and office space. Reliable tile and water-proofing systems were needed to prohibit any water leakage in the towers that cause damage.
Solution:
BAT Tiling worked with ARDEX Australia to offer a SYSTEMARDEX solution. SYSTEMARDEX is a complete regiment of high quality, compatible tiling, flooring and waterproofing products matched with unparalleled technical and field support. Each SystemARDEX product is engineered through meticulous research and developed with feedback from contractors, specifiers, manufacturers and clients. Because of this thorough process, ARDEX customers have full confidence in the quality and end results of SYSTEMARDEX products. Starting with one of the markets fastest drying acrylic membranes, installers applied ARDEX WPM 002 Superflex Bathroom and Balcony Two Part Waterproofing Membrane where needed. ARDEX WPM 002 specifically addresses internal moisture issues under tiles. Because ARDEX WPM 002 is microfiber reinforced, a reinforcing mat is not needed. In non-exposed permanent immersion areas, ARDEX WPM 155 Undertile PU Acrylic Hybrid Membrane was applied. This water-based, polyurethane-acrylic waterproofing membrane was developed for internal and external wet areas for high performance under tile waterproofing. Once the waterproofing membrane was sufficiently dry, screeds were placed throughout the building. To ensure the screeds would have strong bonds, high shears and tensile strengths, ARDEX Abacrete Bonding Agent was added. ARDEX Abacrete is a non-toxic liquid polymer additive designed specifically for use with screeds and renders. This additive also improves water resistance in the flooring. To ensure the tile adhesives would bond appropriately to the substrates, ARDEX Multiprime Water-Based Primer was recommended. ARDEX Multiprime is easy to apply using a sponge, brush or roller. This process saves time and creates a strong bond between the screed and adhesive. Where necessary, ARDEX Abaflex Premium Polymer Modified Flexible Tile Adhesive was applied, and ARDEX DS 40 Impact Sound Reduction and Decoupling system was placed. ARDEX Abaflexs’ eight-hour cure time allows contractors to quickly move forward with the project. ARDEX Abaflex is a good choice because of its flexibility in accommodating cracks (up to .9 mm) created by building movement. ARDEX DS 40 enhanced the luxury of the multipurpose building by reducing impact noise transfer from tenants above. ARDEX DS 40 acoustic mats are pre-cut for easy application and can be placed over various substrates. ARDEX DS 40 can also be directly tiled over using an ARDEX tile adhesive. To accommodate the variety of tiles used in the building, ARDEX X 10 Flexible Non Slump Wall and Floor Tile Adhesive was recommended. ARDEX X 10 is a polymer modified, cement-based wall and floor tile adhesive created with mastic properties ideal for all tile types. The mastic properties prevent sagging and movement in flooring and wall tile installation, maintaining the level of quality required by general contractors. Once tiles were placed, ARDEX grouts were used as the final step. Where pigmented grout was required, ARDEX FG 8 Flexible Colored Grout for Tile Joints 1 to 8 mm wide was used. ARDEX FG 8 may be used on floors and walls and is easy to apply using a rubber trowel. Because it contains anti-mold agents and water repellents, the appearance and overall cleanliness of the rooms is easily maintained. ARDEX FG 8 also cures to a smooth finish reducing the amount of trapped dirt and airborne contaminants. ARDEX Fine Textured Wall Tile Grout was placed in areas that required white grout with a joint size from 1 to 3 mm. This standard grade compressed grout was designed specifically for use on walls, and is an economical choice for ceramic and porcelain tiles. This helps reduce the cost of the project when a specialty grout is not necessary. Wherever a wider joint width occurred, ARDEX Wide Joint Sanded Cement-Based Grout was applied. This grout is shrink-resistant, and is especially suited for wider joints ranging from 5 to 15 mm. It can be used for floor or wall applications, around swimming pools and showers, and is available in a range of colors. For all carpeted areas, ARDEX AF 266 Outdoor Carpet Adhesive was recommended. This water-based adhesive has a low odor, so it is ideal for indoor use. ARDEX recommended this product, because it is resistant to the frequent, commercial grade cleaning expected in a luxury multi-purpose high rise. Each of the products used for this project are part of the SYSTEMARDEX solution. With SYSTEMARDEX, not only are they receiving products that have been manufactured and tested to ARDEX procedures in accordance with Quality System Standard ISO 9001, but they are also warrantied for 10 years. With SYSTEMARDEX warranty and quality assurance, specifiers, contractors and building owners have complete peace of mind knowing that installation was done right the first time, and will withstand heavy use.
AEON Shopping Mall – Vietnam
Project Name:
AEON Mall
Ho Chi Minh City, Vietnam
Installer / Applicator:
Intechem Co Ltd
Featured Products:
ARDEX WPM 160 ARDEX WPM 185
SITUATION:
A well-known chain of shopping malls in Vietnam required waterproofing for deck roof with an A.P.P (atactic polypropylene) membrane.
CHALLENGES:
The project required an A.P.P membrane with high quality and the installation had to be completed after 2 weeks.
SOLUTION:
ARDEX WPM 160 Polyester reinforced APP Bitumen Membrane & ARDEX WPM 185 Mineral coated APP membrane. When torching APP membranes, the bitumen begins to flow like candle wax when it reaches temperatures above 300◦F. The molten bitumen then behaves like hot mopping asphalt and will flow. That makes the job quick, smooth and fast.
McDonald – United Kingdom
Ardex UK has been appointed by the world’s largest family restaurant chain, McDonalds, to supply a tile fixing solution for the re-fit of all of the chain’s UK restaurant locations, having demonstrated expertise and understanding of large scale ‘roll out’ refurbishment programmes, and the necessity to ensure consistency of product, as well as the provision of technical support.
After initial consultations and site visits with the Mcdonald’s Property Team, Ardex proposed and efficient cost and labour saving ‘tile on tile’ solution for the tilling refurbishment. The proposal was supported by product demonstrations to the McDonald’s team. As well as the appointed tiling contractors.
Each refit will commence with the existing wall and floor tiles being cleaned with ardex DGR degreaser. Any damaged tiles will be removed, and the areas patch repaired to level using Ardex Ardurapid A45 rapid hardening and drying internal repair mortar which is able to receive new tiles only 90 minutes after application, regardless of thickness.
To facilitate tile on tile application, Ardex P4 Primer Was specified for use onto the existing tiles. This offer rapid drying of just one hour, enabling the early fixing of new tiles with Ardex X 77 Microtec Flexible Floor & Wall Tile Adhesive. Ardex X 77 has an opentime of up to 60 minutes, providing greater fixing efficiency over large areas, and has been developed to fix heavier, large tiles without slipping.
For the floors, Ardex P 4 Primer was specified for use on the existing floor tiles prior to the application of Ardex Microtec X 78 S Ultra Rapid Setting Floor Tile Adhesive that offers rapid hardening performance that enables tiles to be walked on and grouted after only 90 minutes.
Ardex-Flex FL Rapid Setting Flexible Grout, With Built-in admix, was chosen to fill the tie joints. In addition to offering a colour palette of 32 colours, Ardex-Flex tile grouts incorporate flexibility, water repellence, ease of application and dirt resistance.
H & M,Kallang Wave Sport Hub – Singapore
Project Name:
H&M,
Kallang Wave-Sports Hub Mall – Singapore
Installer:
Coating and Lining
Technologies Pte Ltd – Singapore
Architect:
H&M – Singapore HQ
Featured Products:
ARDEX A 35 Rapid Set Screed Cement
ARDEX R2SE Solvent Free Epoxy Primer
ARDEX R 25 SE Self-Smoothing Epoxy
Floor System
Challenge:
- 200 m2 installation area
- Four – day installation time frame
- Store located on ground level with risks for moisture in slabs
- Multiple trades on the job site
Situation:
H&M Singapore was opening a retail space in the Kallang Wave Mall within Singapore Sports Hub. The distance from the subfloor to the finished floor top level was more not level. The store was located on the ground floor of the mall putting it at issues. Tile installers, heating, vent and air conditioning installers and painting trades functioned simultaneously and had to complete work in four days.
Solution:
To remedy the uneven subfloor, Coating and Lining Technologies used ARDEX A 35 Rapid Set Screed Cement to create an unbonded surface. ARDEX A 35 Rapid Set Screed Cement provides an instant floor, receiving most finished floor materials after only 24 hours. ARDEX A 35 can also be installed as an unbonded screed layer without warping risk. Next, ARDEX R2SE Solvent Free Epoxy Primer was used to seal the substrate preventing air coming out from cement screed pores. ARDEX R 25 SE Self-Smoothing Epoxy coating was installed at varying thicknesses of 2 to 3 mm with no blistering or air bubbles. ARDEX R 25 SE combines outstanding wearing properties with chemical resistance and decorative properties. Ideally suited in areas where a seamless, joint free finish is required and maximum cleanliness is essential.